Refining - Equipment Supply

12,000 BPD Gasoline Production Complex - Pig Launcher & Receiver Package

Iraq
2023
Al Barham Group

Project Scope

Design, Fabrication & Supply

Project Overview

Design, fabrication, testing and supply of a skid-mounted pig launcher and receiver package for a 12,000 BPD gasoline production complex in Iraq. The package brings together mechanical design, 3D piping, isometrics and material takeoffs, pig signalling and monitoring systems, and structural engineering through fabrication and testing.

Key Highlights

  • Refinery capacity: 12,000 barrels per day
  • Complete mechanical design and drawings for Pig Launcher & Receiver
  • 3D piping modeling with isometrics and material takeoffs
  • E&I design for pig signalling and monitoring systems
  • Fabrication, testing, and supply of complete skid-mounted package

Project Gallery

Project Statistics

Refinery Capacity
12,000 BPD
Project Duration
4 Months
Client
Al Barham Group
Scope
Design + Supply

Have a Similar Project in Mind?

Let's discuss how our proven expertise can deliver exceptional results for your next venture